  Western Alignment  

Eastern Alignment

During construction

During construction

  • May require a two-month closure of Saltzman Road at the southern end of the project.
  • Requires an estimated 12-month closure of Saltzman Road (local access allowed).
  • May require one-month lane closure at Laidlaw Road at the new alignment.
  • Detours would require significant out-of-direction travel.

After construction

After construction

  • Connects to NW 130th Avenue.
  • Connects to NW Bannister Avenue.
  • Provides more direct access to Arbor Heights from the south.
  • May include traffic calming measures on Bannister Drive, north of Laidlaw Road.
  • Future improvements to 130th Avenue, north of Laidlaw Road, will be needed.
  • Future improvements to 130th Avenue, north of Laidlaw Road, will be needed.